新桥道口安装整体道口板
施工组织设计
永煤公司铁路运输处
目 录
1 工程施工模式·········································································2
2安装整体道口板工程施工方案···············································2
2.1整体道口板施工人员组织···················································2
2.2整体道口板施工布置平面图···············································3
2.3 整体道口板施工··································································3
2.4施工前准备工作···································································3
2.4.1作业准备···········································································4
2.4.2技术准备···········································································5
2.5材料、机具等摆放位置·························································7
2.6整体道口板铺设纵断面图···················································8
2.7整体道口板铺设施工流程···················································9
2.8铁路验收开通·····································································10
3、施工安全措施·······································································10
3.1铁路方向安全防护·····························································10
3.2公路方向安全防护措施·····················································11
3.3施工现场安全防护措施·····················································11
4施工所需机具、材料·····························································12
4.1所需机具、工器具······························································12
4.2修所需材料··········································································13
新桥道口安装整体道口板施工组织设计
1 工程施工模式
1.1新桥道口属于新桥矿地销公路道口,位于新桥矿铁路专用线DK6+273.4处,现为木枕式橡胶道口板铺面,公路路面宽度12米,公路与铁路为平交,平交道口宽度为12米,由于过往车辆多为拉煤车,载重量大,造成道口铺面板损坏、道口线路病害严重,危极行车安全,为了修复永涡道口破损路面,恢复道口良好状态,保证铁路行车安全,计划对该平交道口铺面进行整体式改造,由铁运处组织施工。
1.2新桥道口为50kg/m钢轨线路,计划采用购进的钢筋混凝土整体道口板和底板,现场吊装铺设,整体道口板①长度为2.5米/块,宽3米,需4块;②长度为2米/块,宽3米,需1块,合计12米,底板共预制12米,使铁路方向整体道口板下部两侧各伸出0.2米,底板下部用半干混凝土压实找平。道口两侧预埋热熔管,具体数量和位置由电务段确定
2安装整体道口板工程施工方案
2.1整体道口板施工人员组织
施工组织领导小组
组长:张 磊
施工负责人:郑伟
成员:任洪俊 李永泉 夏 飞 李亚峰
徐 强 李汉强 杜国昌 孟红光
责任分工:
您可能关注的文档
- 我国游客的不文明现象.ppt
- 我国有色金属牌号和状态.doc
- 沃尔玛_BFSA审核说明.ppt
- 五大分部工程施工质量标准化图集.doc
- 物业经营管理常识.ppt
- 习作_我的心爱之物(部编).ppt
- 现代汉语4形容词.ppt
- 湘教版新版美术九年级(上册)第一课《走下神坛》.ppt
- 项目工程施工联营协议书范本.doc
- 项目公共安全风险评估报告(模板格式)_正式.doc
- 2023年10月四川省洪雅县人力资源和社会保障局从服务基层项目等人员中考核招聘15名乡镇事业单位工作人员5笔试历年高频考点(难、易错点荟萃)附带答案详解.docx
- 平安财险江苏省商业性鹌鹑养殖保险条款.pdf
- 平安产险新疆维吾尔自治区商业性犊牛养殖保险(天莱牧业专属)条款.pdf
- 平安财险江苏省商业性高粱完全成本保险条款.pdf
- 平安产险四川省中央财政补贴性水稻种植保险(融通集团专属)条款.pdf
- 平安产险湖南省新宁县地方财政梅花鹿养殖保险条款.pdf
- 平安产险湖北省洪湖市地方财政补贴性莲藕种植保险条款 .pdf
- 平安产险湖北省当阳市地方财政补贴性柑橘种植保险条款 .pdf
- 平安产险安徽省南陵县地方财政补贴性中稻高温热害气象指数保险条款 .pdf
- 平安财险江苏省常州市金坛区地方财政补贴性水稻补充保额保险条款.pdf
文档评论(0)